In this section
Resources / The Network / Wastewater / Wastewater treatment plants / Moa Point Wastewater Treatment Plant

Moa Point Wastewater Treatment Plant

At the Moa Point Treatment Plant, sewage travels through a series of screens, tanks, bioreactors, clarifiers and ultraviolet treatments before being discharged as liquid into Cook Strait.

It was granted new consents on 11 May 2009. These consents will continue for 25 years (expire 11 May 2034).

In general, the consents allow WCC:

  • to continuously discharge up to 260,000 cubic meters per day of treated and disinfected wastewater into the coastal marine area via an existing submarine outfall,
  • to discharge up to 4500 litres per second of mixed disinfected, treated and milli-screened wastewater to the coastal marine area during and/or immediately after heavy rainfall, when the quantity of wastewater arriving at the Moa Point Wastewater Treatment Plant exceeds 3000 litres per second,
  • to occupy the foreshore and seabed of the coastal marine area with an existing submarine outfall pipeline,
  • to continuously discharge contaminants (including odour) to air from the Moa Point Wastewater Treatment Plant ventilation system.

Resource consents

Resource consent reports

Plant performance



Current Status:
 Non-compliant 
Period: March 2024

Commentary:

The plant remains non-compliant for suspended solids (90-day, 90th percentile limit) since 20 September and for faecal coliforms since 30 October (90-day, 90th percentile limit). The plant became non-compliant for Biochemical Oxygen Demand (BOD) 90-day, 90th percentile limit on 26 February 2024. Process changes to bring effluent back into compliance are being undertaken, however, mechanical failures at the plant are impacting a return to compliance.

Discharges

No discharges in March.

Odour:

No odour complaints in March.


Items of significance:

Clarifier #2 Renewal Project

Structural experts conducted their inspections in March and the subsequent mechanical remedial works required are underway. The planned main bearing and structural replacements will succeed these works with a target completion date of July projected. ​

Inlet Pump Station (IPS) Project

The project commenced late March with Wet Well #1 being taken offline and deep-cleaned. The contractors will establish on site early April to begin the remedial works ahead of fully replacing the two riser pipes. The temporary reduction in the pump station’s discharge capacity does increase the risk of untreated wastewater overflows to the short outfall during heavy rainfall, however expectation is that Wet Well #2 can cope with dry weather flow rates.

Public meeting resources