Lake Ferry Wastewater Treatment

At Lake Ferry the wastewater treatment system consists of on-lot septic tanks with effluent filters and a community wastewater treatment plant. At the treatment plant, septic tank effluent flows through a packed bed reactor, a recirculation tank and ultraviolet treatment. Discharge of the treated effluent is managed to either an adjacent block of land by irrigation or to a constructed wetland, depending on the conditions of the Resource Consents.

The plant was granted new consents on 17 June 2005. A change of conditions was granted on 10 January 2011.  These consents will expire on 30 September 2025.

In general, the consents allow SWDC:

  • to discharge treated wastewater to land via an irrigation system at up to a maximum daily flow rate of 200 cubic meters per day and a maximum weekly flow rate of 700 cubic meters per week.
  • to discharge treated wastewater to land at a maximum application rate of 3.0mm/day or up to the field capacity.
  • to discharge treated wastewater to water (wetland) when the field capacity of the irrigation field has been exceeded or when a discharge is required for emergency or maintenance purposes.
  • to discharge contaminants and odours from the collection, treatment and discharge facilities within the site boundary.

Resource Consents

Plant Performance

 

 

 

 

Current Status: Compliant, but with the risks identified below. 

Period: July 2025

Commentary:

The new resource consent application was submitted this month.

However ongoing work associated with the consent process will be managed by SWDC.

 

Items of significance:

With effect 01 July 2025, SWDC took back ownership of the Capital Delivery Programme and associated projects .

Source of current high inflow and infiltration is still not funded for investigation. Peak loads are impacting on the plant's hydraulic capacity, which is likely to adversely affect the WWTP performance and compliance .

Read the July 2025 Lake Ferry wastewater treatment plant performance monthly report