Projects / Rocky Point Valve Chamber Upgrade

Rocky Point Valve Chamber Upgrade

On behalf of the Greater Wellington Regional Council, we are installing seismically resilient pipe connections to the Rocky Point valve chambers on the Wainuiomata to Wellington water pipeline.
Overview
Current status
Background
All Updates

From July until October 2025, construction work will be taking place adjacent to SH2 between the BP truck stop and the Horokiwi turnoff near Petone, to replace valves in the water main pipe which will make it more resilient to potential earthquake damage.

Start Date
14/07/2025
Contact:

If you have any questions about this work, please contact:

Wellington Water, 04 912 4400

Latest Updates

3 September 2025

26 August 2025

8 August 2025

From July until October 2025, construction work will be taking place adjacent to SH2 between the BP truck stop and the Horokiwi turnoff near Petone, to replace valves in the water main pipe which will make it more resilient to potential earthquake damage. 

Wellington Water in partnership with Brian Perry Civil will be installing seismically resilient pipe connections at two points in the pipeline which carries drinking water from Wainuiomata into Wellington City. 

All lanes on both sides of SH2 will remain open during the construction, however there is a single lane over-night closure for the safety barrier relocation works. There will be no speed reductions in place. Signage will be in place to alert drivers. 

This pipeline feeds drinking water reservoirs in Wellington City, so residents should not experience any outage of water due to these works. 
This project will be followed by work at the Ngauranga Gorge intersection to install further valves. This will start in March 2026 for a period of about 16 weeks to beginning of July. 

 

Work adjacent to SH2 between the truck stop and Horokiwi turnoff, is a part of Wellington Water and Greater Wellington Regional Council’s work to safeguard our water supplies in the event of a large earthquake.

The pipeline bringing water from Wainuiomata into Wellington City running along the side of SH2, has been assessed by engineers and found that it could be vulnerable to liquefaction or lateral movement during a major earthquake

These improvements will replace pipes connections to build resilience in such a way as to allow the pipes to remain intact and working as intended during and after an earthquake.

All Updates

3 September 2025

The first milestone will be achieved by the end of this week with a 22-hour water shutdown to enable the crew to install the first seismic coupler on the east side of the valve chamber.

A second shutdown is schedule for 17 September.

Although the pipe needs to be drained to enable the work to take place, the shutdowns will not impact any users as the local storage will be utilised to maintain supply.

26 August 2025
We're halfway through the three-month project to install earthquake-resilient pipe connections next to SH2, between the BP truck stop and the Horokiwi turnoff! 
Crews are now busy with excavation so that we can start the installation of the seismic resilient couplers early next month.
To install these new pipe connections, we'll need to drain the pipeline and refill once the work is completed. It'll be a slow process to protect the pipe from any damage risk. There will be no impact to water supply as the local storage will be utilised to maintain supply.
   
8 August 2025

The establishing works are progressing well and the site now has the welfare cabins and temporary roads in place.

The safety barriers have been relocated  which have moved the entrance further south to ensure the safety of our crews as they undertake the work.