What is happening?

We are replacing the watermain across Hulls Creek and along Reynolds Bach Drive, Silverstream as part of the Kingsley Water Main Replacement.

This work begins 10 May 2021, and is estimated to be completed 25 March 2022

The works involve pipe construction via open trenching, and construction of two aerial pipe crossings over Hulls Creek and the culvert along Reynolds Bach Drive.

Hours of work will generally be 7am-6pm Monday to Saturday.


June 2022

Work is currently on hold whilst long lead time items for the stream crossings are being purchased. We will be recommencing work as soon as these items arrive. More updates to follow.


November 2021

Most of the pipe has been installed with three key sections left to complete: 

  • Reynolds Bach Drive Stream and Road Crossing
  • Hull’s Creek Pipe Crossing
  • Eastern Hutt Rd Crossing and End Detail