Documents
Here is an archive of documents on the project for viewing and download.
Silverstream Pipeline Replacement Project Assessment of Effects on the Environment - report and separate Appendices
Appendix A - Design report for consent Rev0
Appendix C - Detailed Site Investigation (Bridge and Manor Park)
Appendix D - Assessment of Dewatering Effects
Appendix E - Hydraulic Design Report
Appendix F - Ecological Impact Assessment
Appendix G - Assessment of Natural Character, Landscape and Visual Effects - Graphic Supplement
Appendix H - Archaeological Assessment
Appendix I - Pipeline and Bridge Preliminary Drawings
Appendix J - Regional and District Rules Assessment
Appendix K - Stakeholder Register
Appendix L - Iwi Engagement Correspondence
Appendix M - Silverstream conditions - FINAL
Appendix N - Objectives and Policies
Silverstream Pipeline Replacement Project - Assessment of Effects on the Environment - no Appendices